Project profile
| Client | Aurenne |
|---|---|
| Location | Mt Ida, WA |
| Dates | July 2025 – ongoing |
| S&V role | Electrical scope contractor |
| Team | 5-person crew maintained for 3 months |
| Status | Ongoing – safely and to schedule |
Key scope delivered
- Install & commission 2 x thickeners
- Associated screens, MCC and transformer installation
- 50-room camp upgrade
- New expo office block and toilet / amenities block
- New core shed and assay laboratory
- X-ray machine electrical installation
- Lighting towers throughout site
- Hyper Jet system installation for the plant
- Electrical works to 3 new plant storage tanks
- S&V testing, verification and commissioning records